CONTRACTAMENDED

Final Chimney Rock Road Change Order Reduces Contract

SIMONTON MANAGEMENT DISTRICT 1
Disclosed value
$-41,371.88; new Contract Sum $7,237,377.75
From contract
Document date
Apr 14, 2026

The 30-second brief

What it covers

Fort Bend County processed Change Order No. 2 with Hurtado Construction for the Chimney Rock Road project. The final change order decreases the contract by $41,371.88 to a revised total of $7,237,377.75 and extends the contract time by 255 days to November 14, 2025.

Who holds it

Hurtado Construction holds this construction contract with SIMONTON MANAGEMENT DISTRICT 1. Its other public contracts on record include work for Royalwood Mud and Harris County Mud 165.

What happens next

Term as filed: Contract time increased by 255 days; contract end date changed to 11/14/2025.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$-41,371.88; new Contract Sum $7,237,377.75
Document date
April 14, 2026
Term
Contract time increased by 255 days; contract end date changed to 11/14/2025
Source document
Fort Bend County Contract Change Order 2 Final Change Order to Adjust Bid Items 2026-04-14 (Contract)

Hurtado Construction's other public contracts

More SIMONTON MANAGEMENT DISTRICT 1 contracts

Questions about this contract

Who was awarded the construction contract by SIMONTON MANAGEMENT DISTRICT 1?

Hurtado Construction was awarded this construction contract by SIMONTON MANAGEMENT DISTRICT 1, as recorded on April 14, 2026. The contract value is $-41,371.88; new Contract Sum $7,237,377.75.

How much is the Hurtado Construction contract with SIMONTON MANAGEMENT DISTRICT 1 worth?

The Hurtado Construction contract with SIMONTON MANAGEMENT DISTRICT 1 is valued at $-41,371.88; new Contract Sum $7,237,377.75, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Fort Bend County Contract Change Order 2 Final Change Order to Adjust Bid Items 2026-04-14 (Contract), dated April 14, 2026 from SIMONTON MANAGEMENT DISTRICT 1. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Hurtado Construction hold?

Hurtado Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is SIMONTON MANAGEMENT DISTRICT 1 currently buying?

Explore SIMONTON MANAGEMENT DISTRICT 1's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →