Board Approves Zetron Radio Infrastructure Change Order
- Disclosed value
- $1,396,025.00 (change order); total project cost now $3.9M; additional unbudgeted funding not to exceed $692,000 with 0% third-year financing
- From minutes
- Document date
- Dec 16, 2025
The 30-second brief
The Sedona Fire District Board approved a $1,396,025 change order with Zetron to expand and modernize the radio infrastructure project, bringing the total contract value to $3.9 million. The change order adds P25-compliant components and additional coverage, with up to $692,000 financed at 0% interest in the third year.
ZETRON holds this technology contract with Sedgwick County. Its other public contracts on record include work for City of Walla Walla and Town of Dighton.
Term as filed: Includes third-year financing at 0% interest for $692,000; overall project anticipated to be upgraded by approximately December 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Technology
- Amount
- $1,396,025.00 (change order); total project cost now $3.9M; additional unbudgeted funding not to exceed $692,000 with 0% third-year financing
- Document date
- December 16, 2025
- Term
- Includes third-year financing at 0% interest for $692,000; overall project anticipated to be upgraded by approximately December 2026
- Vendor
- ZETRON
- Agency
- Sedgwick County
- Source document
- Sedona Fire District Board Minutes December 2025 (Minutes)
ZETRON's other public contracts
More Sedgwick County contracts
Questions about this contract
Who was awarded the technology contract by Sedgwick County?
ZETRON was awarded this technology contract by Sedgwick County, as recorded on December 16, 2025. The contract value is $1,396,025.00 (change order); total project cost now $3.9M; additional unbudgeted funding not to exceed $692,000 with 0% third-year financing.
How much is the ZETRON contract with Sedgwick County worth?
The ZETRON contract with Sedgwick County is valued at $1,396,025.00 (change order); total project cost now $3.9M; additional unbudgeted funding not to exceed $692,000 with 0% third-year financing, covering technology work.
What type of contract is this?
This is a Technology contract, documented as a minutes record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in Sedona Fire District Board Minutes December 2025 (Minutes), dated December 16, 2025 from Sedgwick County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does ZETRON hold?
ZETRON may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Sedgwick County currently buying?
Explore Sedgwick County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.