Water Authority Adds $381,383 To Shea Aqueduct Contract
- Disclosed value
- $4,553,905 original; $381,383 added through Change Orders 1–4; $4,935,288 cumulative total
- From agendapacket
- Document date
- Sep 15, 2026
- Term
- September 29, 2025 – February 12, 2027
- Renews
- Free account
The 30-second brief
The Water Authority amended its competitive construction contract with JF Shea Construction for 1st Aqueduct Bifurcation Rehabilitation. Four change orders added $381,383, increasing the cumulative contract value to $4,935,288; the contract runs through February 12, 2027.
Jf Shea Construction holds this construction contract with San Diego Co Water Authority. Its other public contracts on record include work for Cucamonga Valley Water District and Tehama County.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $4,553,905 original; $381,383 added through Change Orders 1–4; $4,935,288 cumulative total
- Document date
- September 15, 2026
- Term
- September 29, 2025 – February 12, 2027
- Renews
- On record
- Vendor
- Jf Shea Construction
- Source document
- San Diego County Water Authority AgendaPacket Board of Directors and Standing Committees Meeting 2026-09-17 (AgendaPacket)
More San Diego Co Water Authority contracts
Questions about this contract
Who was awarded the construction contract by San Diego Co Water Authority?
Jf Shea Construction was awarded this construction contract by San Diego Co Water Authority, as recorded on September 15, 2026. The contract value is $4,553,905 original; $381,383 added through Change Orders 1–4; $4,935,288 cumulative total.
How much is the Jf Shea Construction contract with San Diego Co Water Authority worth?
The Jf Shea Construction contract with San Diego Co Water Authority is valued at $4,553,905 original; $381,383 added through Change Orders 1–4; $4,935,288 cumulative total, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in San Diego County Water Authority AgendaPacket Board of Directors and Standing Committees Meeting 2026-09-17 (AgendaPacket), dated September 15, 2026 from San Diego Co Water Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Jf Shea Construction hold?
Jf Shea Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is San Diego Co Water Authority currently buying?
Explore San Diego Co Water Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.