Aero Mechanical Completes RITBA HVAC Construction
- Disclosed value
- $430,644 revised project budget; original contract amount $415,950
- From agendapacket
- Document date
- Apr 15, 2026
- Term
- Original completion date TBD
The 30-second brief
Aero Mechanical is completing new HVAC construction at RITBA’s Admin Building. The revised project budget is $430,644, and the contractor was addressing punch-list items after installing rooftop units, fans, and controls.
Aero Mechanical holds this construction contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island.
Term as filed: Original completion date TBD.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $430,644 revised project budget; original contract amount $415,950
- Document date
- April 15, 2026
- Term
- Original completion date TBD
- Vendor
- Aero Mechanical
- Source document
- Rhode Island Turnpike and Bridge Authority AgendaPacket Board Meeting April 15, 2026 (AgendaPacket)
Aero Mechanical's other public contracts
More Rhode Island Turnpike and Bridge Authority | State of Rhode Island contracts
Questions about this contract
Who was awarded the construction contract by Rhode Island Turnpike and Bridge Authority | State of Rhode Island?
Aero Mechanical was awarded this construction contract by Rhode Island Turnpike and Bridge Authority | State of Rhode Island, as recorded on April 15, 2026. The contract value is $430,644 revised project budget; original contract amount $415,950.
How much is the Aero Mechanical contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island worth?
The Aero Mechanical contract with Rhode Island Turnpike and Bridge Authority | State of Rhode Island is valued at $430,644 revised project budget; original contract amount $415,950, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Rhode Island Turnpike and Bridge Authority AgendaPacket Board Meeting April 15, 2026 (AgendaPacket), dated April 15, 2026 from Rhode Island Turnpike and Bridge Authority | State of Rhode Island. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Aero Mechanical hold?
Aero Mechanical may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Rhode Island Turnpike and Bridge Authority | State of Rhode Island currently buying?
Explore Rhode Island Turnpike and Bridge Authority | State of Rhode Island's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.