Pearson Kitchen Renovation Change Order Approved for MDI
- Disclosed value
- ($193,288.13) deductive change order; revised total contract amount $5,433,839.87
- From staffreport
- Document date
- Oct 6, 2026
The 30-second brief
Plano Independent School District recommended approving a $193,288.13 deductive change order for MDI General Contractors’ Pearson Early Childhood School kitchen and dining addition and renovation project. The adjustment reduced the total contract amount to $5,433,839.87, with final acceptance and payment authorized after closeout documentation is received.
Mdi General Contractors holds this construction contract with Plano Independent School District. Its other public contracts on record include work for Plano Isd.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- ($193,288.13) deductive change order; revised total contract amount $5,433,839.87
- Document date
- October 6, 2026
- Vendor
- Mdi General Contractors
- Source document
- Plano Independent School District StaffReport Pearson Early Childhood School Kitchen Dining Addition Renovation Change Order No 2 and Closeout 2026-10-06 (StaffReport)
Mdi General Contractors's other public contracts
More Plano Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Plano Independent School District?
Mdi General Contractors was awarded this construction contract by Plano Independent School District, as recorded on October 6, 2026. The contract value is ($193,288.13) deductive change order; revised total contract amount $5,433,839.87.
How much is the Mdi General Contractors contract with Plano Independent School District worth?
The Mdi General Contractors contract with Plano Independent School District is valued at ($193,288.13) deductive change order; revised total contract amount $5,433,839.87, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Plano Independent School District StaffReport Pearson Early Childhood School Kitchen Dining Addition Renovation Change Order No 2 and Closeout 2026-10-06 (StaffReport), dated October 6, 2026 from Plano Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Mdi General Contractors hold?
Mdi General Contractors may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Plano Independent School District currently buying?
Explore Plano Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.