Final Change Order Reduces Cost of Pulis Manhole Project
Northwest Bergen County Utilities AuthorityUtility District · Waldwick, NJ- Disclosed value
- $213,930.66 (final contract cost after $1,069.34 decrease)
- From agendapacket
- Document date
- Aug 5, 2026
The 30-second brief
The Northwest Bergen County Utilities Authority approved a final change order with Joseph M. Sanzari, Inc. for the Pulis Avenue Manhole No. 50 Replacement Project, extending the contract to June 1, 2026 and reducing the total cost to $213,930.66. The amendment reflects contaminated soil disposal and field condition adjustments and authorizes closeout of Contract No. 1167.
Joseph M Sanzari Inc holds this construction contract with Northwest Bergen County Utilities Authority. Its other public contracts on record include work for New Jersey Turnpike Authority and Bergen County Utilities Authority.
Term as filed: Contract extended by 227 days to June 1, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $213,930.66 (final contract cost after $1,069.34 decrease)
- Document date
- August 5, 2026
- Term
- Contract extended by 227 days to June 1, 2026
- Vendor
- Joseph M Sanzari Inc
- Source document
- Northwest Bergen County Utilities Authority AgendaPacket Regular Meeting 2026-08-05 (AgendaPacket)
Joseph M Sanzari Inc's other public contracts
More Northwest Bergen County Utilities Authority contracts
Questions about this contract
Who was awarded the construction contract by Northwest Bergen County Utilities Authority?
Joseph M Sanzari Inc was awarded this construction contract by Northwest Bergen County Utilities Authority, as recorded on August 5, 2026. The contract value is $213,930.66 (final contract cost after $1,069.34 decrease).
How much is the Joseph M Sanzari Inc contract with Northwest Bergen County Utilities Authority worth?
The Joseph M Sanzari Inc contract with Northwest Bergen County Utilities Authority is valued at $213,930.66 (final contract cost after $1,069.34 decrease), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Northwest Bergen County Utilities Authority AgendaPacket Regular Meeting 2026-08-05 (AgendaPacket), dated August 5, 2026 from Northwest Bergen County Utilities Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Joseph M Sanzari Inc hold?
Joseph M Sanzari Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Northwest Bergen County Utilities Authority currently buying?
Explore Northwest Bergen County Utilities Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.