CONTRACTAMENDED

Snow Melter Contract Modification Approved for Colonnelli Brothers

North Hudson Sewerage Authority
Disclosed value
$196,180.00 additional; original contract $593,950.00; revised total $790,130.00
From contract
Document date
Jul 16, 2026
Term
Contract time remains unchanged

The 30-second brief

What it covers

The North Hudson Sewerage Authority approved a $196,180 contract modification for Colonnelli Brothers’ Snow Melter Installation Project. The additional work converts the system to propane and includes site access, retaining wall, roadway, utility protection, and restoration work, increasing the contract total to $790,130 with no change to the contract time.

Who holds it

Colonnelli Brothers holds this construction contract with North Hudson Sewerage Authority.

What happens next

Term as filed: Contract time remains unchanged.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$196,180.00 additional; original contract $593,950.00; revised total $790,130.00
Document date
July 16, 2026
Term
Contract time remains unchanged
Source document
North Hudson Sewerage Authority Contract Modification Resolution Snow Melter Installation Project 2026-07-16 (Contract)

Colonnelli Brothers's other public contracts

More North Hudson Sewerage Authority contracts

Questions about this contract

Who was awarded the construction contract by North Hudson Sewerage Authority?

Colonnelli Brothers was awarded this construction contract by North Hudson Sewerage Authority, as recorded on July 16, 2026. The contract value is $196,180.00 additional; original contract $593,950.00; revised total $790,130.00.

How much is the Colonnelli Brothers contract with North Hudson Sewerage Authority worth?

The Colonnelli Brothers contract with North Hudson Sewerage Authority is valued at $196,180.00 additional; original contract $593,950.00; revised total $790,130.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in North Hudson Sewerage Authority Contract Modification Resolution Snow Melter Installation Project 2026-07-16 (Contract), dated July 16, 2026 from North Hudson Sewerage Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Colonnelli Brothers hold?

Colonnelli Brothers may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is North Hudson Sewerage Authority currently buying?

Explore North Hudson Sewerage Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →