Gerke Sewer Change Order Faces Village Denial
North Freedom villageCity · WI- Disclosed value
- Change order in excess of $117k; approximately $30k+ attributed to the changed drill path
- From minutes
- Document date
- Sep 14, 2026
The 30-second brief
Gerke submitted a change order exceeding $117,000 for the South Maple sewer relocation project, citing unforeseen drilling conditions. MSA challenged the request, and Village officials indicated the change order would be denied while the project proceeds toward October closeout.
GERKE holds this construction contract with North Freedom village. Its other public contracts on record include work for La Crosse Housing Authority and City of Port Aransas.
Term as filed: 15-day time extension requested; substantial completion planned for September 19, 2026, with project closeout planned for October 17, 2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change order in excess of $117k; approximately $30k+ attributed to the changed drill path
- Document date
- September 14, 2026
- Term
- 15-day time extension requested; substantial completion planned for September 19, 2026, with project closeout planned for October 17, 2026
- Vendor
- GERKE
- Agency
- North Freedom village
- Source document
- Village of North Freedom Minutes Regular Board Meeting September 14, 2026 (Minutes)
GERKE's other public contracts
More North Freedom village contracts
Questions about this contract
Who was awarded the construction contract by North Freedom village?
GERKE was awarded this construction contract by North Freedom village, as recorded on September 14, 2026. The contract value is Change order in excess of $117k; approximately $30k+ attributed to the changed drill path.
How much is the GERKE contract with North Freedom village worth?
The GERKE contract with North Freedom village is valued at Change order in excess of $117k; approximately $30k+ attributed to the changed drill path, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Village of North Freedom Minutes Regular Board Meeting September 14, 2026 (Minutes), dated September 14, 2026 from North Freedom village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does GERKE hold?
GERKE may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is North Freedom village currently buying?
Explore North Freedom village's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.