B&B High Voltage Quote Not Selected for Pole Replacement
- Disclosed value
- $140,610.00, plus additional subcontractor costs for drilling; subcontracting costs are estimated to exceed $50,000
- From staffreport
- Document date
- Oct 28, 2026
The 30-second brief
B&B High Voltage submitted a $140,610 quote for Nevada Irrigation District’s Bowman Transmission Line power pole replacement project, with additional drilling subcontractor costs expected to exceed $50,000. Staff selected another contractor for the work based on the overall estimated approach and price comparison.
B&b High Voltage holds this construction contract with Nevada Irrigation District.
Term as filed: November 2-7, 2026 (tentatively scheduled).
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $140,610.00, plus additional subcontractor costs for drilling; subcontracting costs are estimated to exceed $50,000
- Document date
- October 28, 2026
- Term
- November 2-7, 2026 (tentatively scheduled)
- Vendor
- B&b High Voltage
- Source document
- Nevada Irrigation District Staff Report Award of Contract for Bowman Transmission Line Power Pole Replacement (Project #C0062) 2026-10-28 (StaffReport)
More Nevada Irrigation District contracts
Questions about this contract
Who was awarded the construction contract by Nevada Irrigation District?
B&b High Voltage was awarded this construction contract by Nevada Irrigation District, as recorded on October 28, 2026. The contract value is $140,610.00, plus additional subcontractor costs for drilling; subcontracting costs are estimated to exceed $50,000.
How much is the B&b High Voltage contract with Nevada Irrigation District worth?
The B&b High Voltage contract with Nevada Irrigation District is valued at $140,610.00, plus additional subcontractor costs for drilling; subcontracting costs are estimated to exceed $50,000, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Nevada Irrigation District Staff Report Award of Contract for Bowman Transmission Line Power Pole Replacement (Project #C0062) 2026-10-28 (StaffReport), dated October 28, 2026 from Nevada Irrigation District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is Nevada Irrigation District currently buying?
Explore Nevada Irrigation District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.