Alex Paris Advances Waterline and Pipeline Work
- Document date
- Jun 29, 2020
The 30-second brief
Contractor Alex Paris is installing plastic waterline and steel pipeline for the agency’s project, including preparation for Stream Crossing 4 and concurrent welding work following mobilization on June 21. The report notes 700 feet of waterline installed out of 6,000 planned feet.
Paris, Alex holds this construction contract with Municipal Authority Of Westmoreland County. Its other public contracts on record include work for City of Follansbee and Town of North Franklin.
Hear about the next contract at Municipal Authority Of Westmoreland County early.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- June 29, 2020
- Vendor
- Paris, Alex
- Source document
- MAWC Drilling Sites Activity Report June 29 2020 (Report)
Paris, Alex's other public contracts
More Municipal Authority Of Westmoreland County contracts
Questions about this contract
Who was awarded the construction contract by Municipal Authority Of Westmoreland County?
Paris, Alex was awarded this construction contract by Municipal Authority Of Westmoreland County, as recorded on June 29, 2020.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in MAWC Drilling Sites Activity Report June 29 2020 (Report), dated June 29, 2020 from Municipal Authority Of Westmoreland County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What is Municipal Authority Of Westmoreland County currently buying?
Explore Municipal Authority Of Westmoreland County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.