CONTRACTAMENDED

Concrete Repair Change Order Approved for Medford Construction

Kern Community College District logoKern Community College District
Disclosed value
$7,375.00 change order; revised contract amount $233,625.00
From contract
Document date
Sep 16, 2026

The 30-second brief

What it covers

Kern Community College District documented Change Order No. 1 with Medford Construction, Inc. for additional concrete and mow curb repairs at Bakersfield College. The $7,375 change increases the contract to $233,625 and adds 30 days, revising completion to August 15, 2026.

Who holds it

Medford Construction Inc holds this construction contract with Kern Community College District. Its other public contracts on record include work for Bakersfield College and Kern High.

What happens next

Term as filed: 30 days added; revised completion date August 15, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$7,375.00 change order; revised contract amount $233,625.00
Document date
September 16, 2026
Term
30 days added; revised completion date August 15, 2026
Source document
Kern Community College District Contract Change Order Bakersfield College SMSR 2022-23 Concrete Replacement Campuswide 2026-09-16 (Contract)

Medford Construction Inc's other public contracts

More Kern Community College District contracts

Questions about this contract

Who was awarded the construction contract by Kern Community College District?

Medford Construction Inc was awarded this construction contract by Kern Community College District, as recorded on September 16, 2026. The contract value is $7,375.00 change order; revised contract amount $233,625.00.

How much is the Medford Construction Inc contract with Kern Community College District worth?

The Medford Construction Inc contract with Kern Community College District is valued at $7,375.00 change order; revised contract amount $233,625.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Kern Community College District Contract Change Order Bakersfield College SMSR 2022-23 Concrete Replacement Campuswide 2026-09-16 (Contract), dated September 16, 2026 from Kern Community College District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Medford Construction Inc hold?

Medford Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Kern Community College District currently buying?

Explore Kern Community College District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →