CONTRACTAPPROVED

JEFFERSON WATER-SEWER DIST Awards Professional Services Contract to Franklin County Engineer (June 2026)

JEFFERSON WATER-SEWER DIST logoJEFFERSON WATER-SEWER DIST
Disclosed value
Not to exceed $463,053.00; design reimbursement $12,233.00; engineer’s estimate for JWSD WORK construction $450,820.00
From resolution
Approved
Jun 18, 2026

The 30-second brief

What it covers

Jefferson Water and Sewer District approved Resolution 2026-27 to enter into a cooperative agreement with the Franklin County Engineer for engineering design, bidding, and construction administration of water and sanitary sewer relocations for the Clark State Road and Waggoner Road Roundabout Project, with expenditures capped at $463,053.00. Under the agreement, JWSD will reimburse the County for design costs and its share of construction while the County manages bidding and construction oversight.

Who holds it

Franklin County Engineer holds this professional services contract with JEFFERSON WATER-SEWER DIST. Its other public contracts on record include work for Town of Mifflin and Town of Jefferson.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Professional Services
Amount
Not to exceed $463,053.00; design reimbursement $12,233.00; engineer’s estimate for JWSD WORK construction $450,820.00
Document date
June 18, 2026
Source document
Jefferson Water and Sewer District Resolution 2026-27 Clark State Road and Waggoner Road Roundabout Project 2026-06-18 (Resolution)

Franklin County Engineer's other public contracts

More JEFFERSON WATER-SEWER DIST contracts

Questions about this contract

Who was awarded the professional services contract by JEFFERSON WATER-SEWER DIST?

Franklin County Engineer was awarded this professional services contract by JEFFERSON WATER-SEWER DIST, as recorded on June 18, 2026. The contract value is Not to exceed $463,053.00; design reimbursement $12,233.00; engineer’s estimate for JWSD WORK construction $450,820.00.

How much is the Franklin County Engineer contract with JEFFERSON WATER-SEWER DIST worth?

The Franklin County Engineer contract with JEFFERSON WATER-SEWER DIST is valued at Not to exceed $463,053.00; design reimbursement $12,233.00; engineer’s estimate for JWSD WORK construction $450,820.00, covering professional services work.

What type of contract is this?

This is a Professional Services contract, documented as a resolution record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Jefferson Water and Sewer District Resolution 2026-27 Clark State Road and Waggoner Road Roundabout Project 2026-06-18 (Resolution), dated June 18, 2026 from JEFFERSON WATER-SEWER DIST. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Franklin County Engineer hold?

Franklin County Engineer may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is JEFFERSON WATER-SEWER DIST currently buying?

Explore JEFFERSON WATER-SEWER DIST's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.