CONTRACTPENDING

JTA Seeks BSIC Claim Settlement With Balfour Beatty

Jacksonville Transportation Authority logoJacksonville Transportation Authority
Disclosed value
$2,672,826 settlement amount; original claim/change order was $5,234,173
From minutes
Document date
Feb 26, 2026
Term
Extended through June 30, 2026

The 30-second brief

What it covers

The Jacksonville Transportation Authority reached a pending agreement with Balfour Beatty Construction to settle a BSIC supervening-events claim for $2,672,826, reduced from the original $5,234,173 claim. The proposed amendment would extend the contract through June 30, 2026, subject to Board approval.

Who holds it

Balfour Beatty Construction holds this construction contract with Jacksonville Transportation Authority. Its other public contracts on record include work for San Diego County and Chatham County School District.

What happens next

Term as filed: Extended through June 30, 2026.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$2,672,826 settlement amount; original claim/change order was $5,234,173
Document date
February 26, 2026
Term
Extended through June 30, 2026
Source document
Jacksonville Transportation Authority Minutes Board Work Session 2026-02-26 (Minutes)

Balfour Beatty Construction's other public contracts

More Jacksonville Transportation Authority contracts

Questions about this contract

Who was awarded the construction contract by Jacksonville Transportation Authority?

Balfour Beatty Construction was awarded this construction contract by Jacksonville Transportation Authority, as recorded on February 26, 2026. The contract value is $2,672,826 settlement amount; original claim/change order was $5,234,173.

How much is the Balfour Beatty Construction contract with Jacksonville Transportation Authority worth?

The Balfour Beatty Construction contract with Jacksonville Transportation Authority is valued at $2,672,826 settlement amount; original claim/change order was $5,234,173, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Jacksonville Transportation Authority Minutes Board Work Session 2026-02-26 (Minutes), dated February 26, 2026 from Jacksonville Transportation Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Balfour Beatty Construction hold?

Balfour Beatty Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Jacksonville Transportation Authority currently buying?

Explore Jacksonville Transportation Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →