JEA Approves $7.8 Million Force Main Change Order
- Disclosed value
- Change order amount $7,843,769.81; new cumulative amount $9,407,668.60
- From agenda
- Document date
- May 22, 2025
The 30-second brief
JEA approved a $7.84 million change order with Ferreira Construction Southern Division, Inc. for rehabilitation of the McMillan Street Pump Station force main. The change moves the project to a predominantly cured-in-place pipe method and raises the cumulative contract value to $9.41 million.
Ferreira Construction Southern Division Inc holds this construction contract with Jacksonville Electric Authority (JEA) - Procurement Dept.
Term as filed: Project completion; Start: 02/22/2024; End: 08/30/2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change order amount $7,843,769.81; new cumulative amount $9,407,668.60
- Document date
- May 22, 2025
- Term
- Project completion; Start: 02/22/2024; End: 08/30/2025
- Source document
- JEA Agenda 2025-05-22 (Agenda)
Ferreira Construction Southern Division Inc's other public contracts
More Jacksonville Electric Authority (JEA) - Procurement Dept contracts
Questions about this contract
Who was awarded the construction contract by Jacksonville Electric Authority (JEA) - Procurement Dept?
Ferreira Construction Southern Division Inc was awarded this construction contract by Jacksonville Electric Authority (JEA) - Procurement Dept, as recorded on May 22, 2025. The contract value is Change order amount $7,843,769.81; new cumulative amount $9,407,668.60.
How much is the Ferreira Construction Southern Division Inc contract with Jacksonville Electric Authority (JEA) - Procurement Dept worth?
The Ferreira Construction Southern Division Inc contract with Jacksonville Electric Authority (JEA) - Procurement Dept is valued at Change order amount $7,843,769.81; new cumulative amount $9,407,668.60, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in JEA Agenda 2025-05-22 (Agenda), dated May 22, 2025 from Jacksonville Electric Authority (JEA) - Procurement Dept. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ferreira Construction Southern Division Inc hold?
Ferreira Construction Southern Division Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Jacksonville Electric Authority (JEA) - Procurement Dept currently buying?
Explore Jacksonville Electric Authority (JEA) - Procurement Dept's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.