CONTRACTAMENDED

Fire Station GMP Amendment Approved for Inline

Hoodland Fire District #74 logoHoodland Fire District #74
Document date
Aug 11, 2026

The 30-second brief

What it covers

Hoodland Fire District approved GMP Amendment #2 with Inline for the fire station project. The amendment reflected favorable subcontractor market conditions and an estimate that was coming in under budget; no amendment amount was stated.

Who holds it

INLINE holds this construction contract with Hoodland Fire District #74. Its other public contracts on record include work for Bremen village.

Hear about the next contract at Hoodland Fire District #74 early.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
August 11, 2026
Vendor
INLINE
Source document
Hoodland Fire District Minutes Board Meeting August 11, 2026 (Minutes)

INLINE's other public contracts

More Hoodland Fire District #74 contracts

Questions about this contract

Who was awarded the construction contract by Hoodland Fire District #74?

INLINE was awarded this construction contract by Hoodland Fire District #74, as recorded on August 11, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Hoodland Fire District Minutes Board Meeting August 11, 2026 (Minutes), dated August 11, 2026 from Hoodland Fire District #74. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does INLINE hold?

INLINE may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is Hoodland Fire District #74 currently buying?

Explore Hoodland Fire District #74's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →