CONTRACTAMENDED

UDN General Contract for Phase 3.C Significantly Amended

Honeoye Falls-Lima Central School District logoHoneoye Falls-Lima Central School District
Disclosed value
$3,520,000 (original); revised $3,905,582 after $385,582 in change orders for Phase 3.C Contract #303
From report
Document date
Jun 1, 2026

The 30-second brief

What it covers

UDN’s Phase 3.C general construction Contract #303 at Lima and the Middle School has been increased to $3,905,582 after $385,582 in change orders. Work includes cafeteria renovations, classroom reconfigurations, and structural and abatement adjustments.

Who holds it

UDN holds this construction contract with Honeoye Falls-Lima Central School District. Its other public contracts on record include work for Ridge Road Fire District.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$3,520,000 (original); revised $3,905,582 after $385,582 in change orders for Phase 3.C Contract #303
Document date
June 1, 2026
Vendor
UDN
Source document
Honeoye Falls-Lima Central School District Phase 3.0 Capital Improvement Project Progress Report June 2026 (Report)

UDN's other public contracts

More Honeoye Falls-Lima Central School District contracts

Questions about this contract

Who was awarded the construction contract by Honeoye Falls-Lima Central School District?

UDN was awarded this construction contract by Honeoye Falls-Lima Central School District, as recorded on June 1, 2026. The contract value is $3,520,000 (original); revised $3,905,582 after $385,582 in change orders for Phase 3.C Contract #303.

How much is the UDN contract with Honeoye Falls-Lima Central School District worth?

The UDN contract with Honeoye Falls-Lima Central School District is valued at $3,520,000 (original); revised $3,905,582 after $385,582 in change orders for Phase 3.C Contract #303, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Honeoye Falls-Lima Central School District Phase 3.0 Capital Improvement Project Progress Report June 2026 (Report), dated June 1, 2026 from Honeoye Falls-Lima Central School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does UDN hold?

UDN may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Honeoye Falls-Lima Central School District currently buying?

Explore Honeoye Falls-Lima Central School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →