CONTRACTAMENDED

LG Evans Multi-Site Sitework Contract Amended

Honeoye Falls-Lima Central School District logoHoneoye Falls-Lima Central School District
Disclosed value
$2,199,900 (original); revised $2,292,532 after $92,632 in change orders for Contract #301
From report
Document date
Jun 1, 2026

The 30-second brief

What it covers

LG Evans’ Phase 3.C sitework Contract #301 across Lima, Manor, and the Middle School now totals $2,292,532 after $92,632 in change orders. Adjustments reflect unforeseen subsurface conditions and owner-requested site enhancements.

Who holds it

Lg Evans holds this construction contract with Honeoye Falls-Lima Central School District. Its other public contracts on record include work for Newark Housing Authority.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$2,199,900 (original); revised $2,292,532 after $92,632 in change orders for Contract #301
Document date
June 1, 2026
Vendor
Lg Evans
Source document
Honeoye Falls-Lima Central School District Phase 3.0 Capital Improvement Project Progress Report June 2026 (Report)

Lg Evans's other public contracts

More Honeoye Falls-Lima Central School District contracts

Questions about this contract

Who was awarded the construction contract by Honeoye Falls-Lima Central School District?

Lg Evans was awarded this construction contract by Honeoye Falls-Lima Central School District, as recorded on June 1, 2026. The contract value is $2,199,900 (original); revised $2,292,532 after $92,632 in change orders for Contract #301.

How much is the Lg Evans contract with Honeoye Falls-Lima Central School District worth?

The Lg Evans contract with Honeoye Falls-Lima Central School District is valued at $2,199,900 (original); revised $2,292,532 after $92,632 in change orders for Contract #301, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Honeoye Falls-Lima Central School District Phase 3.0 Capital Improvement Project Progress Report June 2026 (Report), dated June 1, 2026 from Honeoye Falls-Lima Central School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Lg Evans hold?

Lg Evans may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.