- Disclosed value
- $669,900, including 10% contingency
- From staffreport
- Approved
- Sep 3, 2026
- Term
- December 2026 – January 2027
The 30-second brief
Heartland Community College approved a $669,900 construction bid for Weber Electric to complete Phase I of the ACEC Auditorium Upgrades Project. Work includes LED lighting, stage-lighting controls, and replacement of the main sound mixing board, with construction scheduled for December 2026 through January 2027.
Weber Electric holds this construction contract with Heartland Community College. Its other public contracts on record include work for Housing Authority of the city of Bloomington, IL and Town of Funks Grove.
Term as filed: December 2026 – January 2027.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $669,900, including 10% contingency
- Document date
- September 3, 2026
- Term
- December 2026 – January 2027
- Vendor
- Weber Electric
- Source document
- Heartland Community College StaffReport Approval of ACEC Auditorium Upgrades Project Phase I Bids 2026-09-03 (StaffReport)
Weber Electric's other public contracts
More Heartland Community College contracts
Questions about this contract
Who was awarded the construction contract by Heartland Community College?
Weber Electric was awarded this construction contract by Heartland Community College, as recorded on September 3, 2026. The contract value is $669,900, including 10% contingency.
How much is the Weber Electric contract with Heartland Community College worth?
The Weber Electric contract with Heartland Community College is valued at $669,900, including 10% contingency, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Heartland Community College StaffReport Approval of ACEC Auditorium Upgrades Project Phase I Bids 2026-09-03 (StaffReport), dated September 3, 2026 from Heartland Community College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Weber Electric hold?
Weber Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Heartland Community College currently buying?
Explore Heartland Community College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.