CONTRACTONGOING

Biosolids Construction Project Nears Completion with Gateway Pacific

Goleta Sanitary District
Disclosed value
$12,762,250 total project construction cost including executed change orders to date; original estimated construction cost $12,773,870
From agendapacket
Document date
Oct 19, 2026
Renews
Free account

The 30-second brief

What it covers

Goleta Sanitary District continues its Biosolids and Energy Strategic Plan Phase 1 construction project with Gateway Pacific Contractors. Construction costs, including executed change orders, total $12,762,250, with completion expected in November 2026.

Who holds it

Gateway Pacific Contractors holds this construction contract with Goleta Sanitary District. Its other public contracts on record include work for Goleta West Sanitary District.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every Goleta Sanitary District contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$12,762,250 total project construction cost including executed change orders to date; original estimated construction cost $12,773,870
Document date
October 19, 2026
Term
Construction began in 2023; estimated completion November 2026
Renews
Free account
Source document
Goleta Sanitary District AgendaPacket 2026-10-19 (AgendaPacket)

Gateway Pacific Contractors's other public contracts

More Goleta Sanitary District contracts

Questions about this contract

Who was awarded the construction contract by Goleta Sanitary District?

Gateway Pacific Contractors was awarded this construction contract by Goleta Sanitary District, as recorded on October 19, 2026. The contract value is $12,762,250 total project construction cost including executed change orders to date; original estimated construction cost $12,773,870.

How much is the Gateway Pacific Contractors contract with Goleta Sanitary District worth?

The Gateway Pacific Contractors contract with Goleta Sanitary District is valued at $12,762,250 total project construction cost including executed change orders to date; original estimated construction cost $12,773,870, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Goleta Sanitary District AgendaPacket 2026-10-19 (AgendaPacket), dated October 19, 2026 from Goleta Sanitary District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Gateway Pacific Contractors hold?

Gateway Pacific Contractors may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Goleta Sanitary District currently buying?

Explore Goleta Sanitary District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →