Gateway Pacific Nears Completion Of $12.76M Digester Project

Goleta Sanitary District
Disclosed value
$12,762,250 including executed change orders to date; original estimated construction cost $12,773,870
From agendapacket
Document date
Jul 20, 2026

The 30-second brief

What it covers

Gateway Pacific Contractors is nearing completion of the Goleta Sanitary District’s Biosolids and Energy Strategic Plan Phase 1 construction project. Executed change orders have brought construction costs to $12.76 million, with completion expected in July 2026 and commissioning in August.

Who holds it

Gateway Pacific Contractors holds this construction contract with Goleta Sanitary District. Its other public contracts on record include work for Goleta West Sanitary District.

What happens next

Term as filed: Construction began in 2023; completion estimated July 2026, with commissioning complete August 2026.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$12,762,250 including executed change orders to date; original estimated construction cost $12,773,870
Document date
July 20, 2026
Term
Construction began in 2023; completion estimated July 2026, with commissioning complete August 2026
Source document
Goleta Sanitary District AgendaPacket Regular Meeting of the Governing Board 2026-07-20 (AgendaPacket)

Gateway Pacific Contractors's other public contracts

More Goleta Sanitary District contracts

Questions about this contract

Who was awarded the construction contract by Goleta Sanitary District?

Gateway Pacific Contractors was awarded this construction contract by Goleta Sanitary District, as recorded on July 20, 2026. The contract value is $12,762,250 including executed change orders to date; original estimated construction cost $12,773,870.

How much is the Gateway Pacific Contractors contract with Goleta Sanitary District worth?

The Gateway Pacific Contractors contract with Goleta Sanitary District is valued at $12,762,250 including executed change orders to date; original estimated construction cost $12,773,870, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Goleta Sanitary District AgendaPacket Regular Meeting of the Governing Board 2026-07-20 (AgendaPacket), dated July 20, 2026 from Goleta Sanitary District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Gateway Pacific Contractors hold?

Gateway Pacific Contractors may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Goleta Sanitary District currently buying?

Explore Goleta Sanitary District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →