Gideon Welles Roof Project Reported Complete
- Disclosed value
- $2,500,000 grant award; final construction cost $2,429,555; approximately $789,605 expected reimbursement
- From staffreport
- Document date
- Sep 14, 2026
The 30-second brief
The Glastonbury Board of Education reported completion of the Gideon Welles School roof replacement project for state grant closeout. The project carried a $2.5 million grant award, with final construction costs of $2,429,555 and an estimated $789,605 in state reimbursement.
ARCHITECT holds this construction contract with Glastonbury School District. Its other public contracts on record include work for Devils Lake Public School District 1 and Oklahoma County.
Term as filed: Project completed in fall 2025; fascia panels completed spring 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $2,500,000 grant award; final construction cost $2,429,555; approximately $789,605 expected reimbursement
- Document date
- September 14, 2026
- Term
- Project completed in fall 2025; fascia panels completed spring 2026
- Vendor
- ARCHITECT
- Source document
- Glastonbury Board of Education StaffReport Acceptance of Gideon Welles Roof Replacement Project as Completed 2026-09-14 (StaffReport)
ARCHITECT's other public contracts
More Glastonbury School District contracts
Questions about this contract
Who was awarded the construction contract by Glastonbury School District?
ARCHITECT was awarded this construction contract by Glastonbury School District, as recorded on September 14, 2026. The contract value is $2,500,000 grant award; final construction cost $2,429,555; approximately $789,605 expected reimbursement.
How much is the ARCHITECT contract with Glastonbury School District worth?
The ARCHITECT contract with Glastonbury School District is valued at $2,500,000 grant award; final construction cost $2,429,555; approximately $789,605 expected reimbursement, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Glastonbury Board of Education StaffReport Acceptance of Gideon Welles Roof Replacement Project as Completed 2026-09-14 (StaffReport), dated September 14, 2026 from Glastonbury School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does ARCHITECT hold?
ARCHITECT may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Glastonbury School District currently buying?
Explore Glastonbury School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.