Roof Projects Contract Reduced by $80,000
- Disclosed value
- Decrease of $80,000.00; new Contract Sum $1,738,000.00 (original Contract Sum $1,818,000.00)
- From contract
- Document date
- Aug 10, 2026
The 30-second brief
Frisco Independent School District amended Advantage USAA's storm-related roof projects contract for Pearson MS and Ellison CDC. The change order deducts $80,000 in unused contingency, reducing the contract sum from $1,818,000 to $1,738,000, with substantial completion set for August 25, 2026.
Advantage Usaa Inc holds this construction contract with Frisco Independent School District. Its other public contracts on record include work for Eagle Mountain-Saginaw Independent School District and Harris Co Mta Non-Union Pension Plan.
Term as filed: Through substantial completion on August 25, 2026; contract time unchanged.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Decrease of $80,000.00; new Contract Sum $1,738,000.00 (original Contract Sum $1,818,000.00)
- Document date
- August 10, 2026
- Term
- Through substantial completion on August 25, 2026; contract time unchanged
- Vendor
- Advantage Usaa Inc
- Source document
- Frisco Independent School District Contract Change Order Storm Related Roof Projects 2026-08-10 (Contract)
Advantage Usaa Inc's other public contracts
More Frisco Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Frisco Independent School District?
Advantage Usaa Inc was awarded this construction contract by Frisco Independent School District, as recorded on August 10, 2026. The contract value is Decrease of $80,000.00; new Contract Sum $1,738,000.00 (original Contract Sum $1,818,000.00).
How much is the Advantage Usaa Inc contract with Frisco Independent School District worth?
The Advantage Usaa Inc contract with Frisco Independent School District is valued at Decrease of $80,000.00; new Contract Sum $1,738,000.00 (original Contract Sum $1,818,000.00), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Frisco Independent School District Contract Change Order Storm Related Roof Projects 2026-08-10 (Contract), dated August 10, 2026 from Frisco Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Advantage Usaa Inc hold?
Advantage Usaa Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Frisco Independent School District currently buying?
Explore Frisco Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.