Pipeline Constructors Releases Phase 1 Infrastructure Claims
Coquina Shores Community Development DistrictSpecial District · Tallahassee, FL- Disclosed value
- $10,950,714.36 total reimbursable cost for listed Phase 1 improvements
- From agendapacket
- Document date
- Oct 15, 2026
The 30-second brief
Pipeline Constructors, Inc. constructed Coquina Shores Phase 1 utility and site improvements under a 2025 work order. The contractor’s October 2026 release confirms payment and transfers reliance on applicable warranties to the district after acquisition.
Pipeline Constructors Inc holds this construction contract with Coquina Shores Community Development District.
Term as filed: Contract dated August 6, 2025 under Master Trade Agreement dated May 2, 2018; release effective upon execution.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $10,950,714.36 total reimbursable cost for listed Phase 1 improvements
- Document date
- October 15, 2026
- Term
- Contract dated August 6, 2025 under Master Trade Agreement dated May 2, 2018; release effective upon execution
- Source document
- Coquina Shores Community Development District AgendaPacket October 15, 2026 (AgendaPacket)
Pipeline Constructors Inc's other public contracts
More Coquina Shores Community Development District contracts
Questions about this contract
Who was awarded the construction contract by Coquina Shores Community Development District?
Pipeline Constructors Inc was awarded this construction contract by Coquina Shores Community Development District, as recorded on October 15, 2026. The contract value is $10,950,714.36 total reimbursable cost for listed Phase 1 improvements.
How much is the Pipeline Constructors Inc contract with Coquina Shores Community Development District worth?
The Pipeline Constructors Inc contract with Coquina Shores Community Development District is valued at $10,950,714.36 total reimbursable cost for listed Phase 1 improvements, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Coquina Shores Community Development District AgendaPacket October 15, 2026 (AgendaPacket), dated October 15, 2026 from Coquina Shores Community Development District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Pipeline Constructors Inc hold?
Pipeline Constructors Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Coquina Shores Community Development District currently buying?
Explore Coquina Shores Community Development District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.