CONTRACTRECOMMENDED

HVAC Replacement Contract Recommended for Jamail & Smith

Clear Creek Independent School District logoClear Creek Independent School District
Disclosed value
$3,046,000; base proposal $3,700,000 less Alternate #1 deduction of $710,000, plus Alternate #2 of $36,000 and Alternate #3 of $20,000
From staffreport
Document date
Oct 26, 2026
Term
Substantial completion by July 31, 2027
Renews
Free account

The 30-second brief

What it covers

Clear Creek Independent School District recommends awarding Jamail & Smith Construction a $3,046,000 contract for the MDF/IDF HVAC Replacement Phase 3 Project. The project is funded by 2023 bond funds and must reach substantial completion by July 31, 2027.

Who holds it

Jamail & Smith Construction holds this construction contract with Clear Creek Independent School District. Its other public contracts on record include work for Elgin Independent School District and Mendez Middle.

What happens next

The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.

Renewal date on recordLocked

Get pre-RFPs for work like this before the bid is out.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$3,046,000; base proposal $3,700,000 less Alternate #1 deduction of $710,000, plus Alternate #2 of $36,000 and Alternate #3 of $20,000
Document date
October 26, 2026
Term
Substantial completion by July 31, 2027
Renews
On record
Source document
Clear Creek Independent School District StaffReport Consider Approval of Construction Contract 2027.400 for the MDF/IDF HVAC Replacement Phase 3 Project 2026-10-26 (StaffReport)

Jamail & Smith Construction's other public contracts

More Clear Creek Independent School District contracts

Questions about this contract

Who was awarded the construction contract by Clear Creek Independent School District?

Jamail & Smith Construction was awarded this construction contract by Clear Creek Independent School District, as recorded on October 26, 2026. The contract value is $3,046,000; base proposal $3,700,000 less Alternate #1 deduction of $710,000, plus Alternate #2 of $36,000 and Alternate #3 of $20,000.

How much is the Jamail & Smith Construction contract with Clear Creek Independent School District worth?

The Jamail & Smith Construction contract with Clear Creek Independent School District is valued at $3,046,000; base proposal $3,700,000 less Alternate #1 deduction of $710,000, plus Alternate #2 of $36,000 and Alternate #3 of $20,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Clear Creek Independent School District StaffReport Consider Approval of Construction Contract 2027.400 for the MDF/IDF HVAC Replacement Phase 3 Project 2026-10-26 (StaffReport), dated October 26, 2026 from Clear Creek Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Jamail & Smith Construction hold?

Jamail & Smith Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Clear Creek Independent School District currently buying?

Explore Clear Creek Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →