Wastewater Change Order Proposed for S & L Underground
- Disclosed value
- $514,300.00 increase; contract price increases from $13,117,301.55 to $13,131,601.55 as stated in Change Order No. 5
- From report
- Document date
- Nov 5, 2026
The 30-second brief
Thompson Falls is considering Change Order No. 5 with S & L Underground for the Phases 3 and 4 wastewater improvements project. The change order states a $514,300 contract increase and adds 99 calendar days for field changes, sewer insulation, remobilization and construction delays.
S & L Underground holds this construction contract with City of Thompson Falls. Its other public contracts on record include work for Lodi Area Emergency Medical Service and City of Lodi.
Term as filed: 99 additional calendar days; substantial completion increases to 603 days and ready-for-final-payment increases to 633 days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $514,300.00 increase; contract price increases from $13,117,301.55 to $13,131,601.55 as stated in Change Order No. 5
- Document date
- November 5, 2026
- Term
- 99 additional calendar days; substantial completion increases to 603 days and ready-for-final-payment increases to 633 days
- Vendor
- S & L Underground
- Agency
- City of Thompson Falls
- Source document
- Thompson Falls Report Summary of encroachment complaint in Mountain View Townsite 2026-11-05 (Report)
S & L Underground's other public contracts
More City of Thompson Falls contracts
Questions about this contract
Who was awarded the construction contract by City of Thompson Falls?
S & L Underground was awarded this construction contract by City of Thompson Falls, as recorded on November 5, 2026. The contract value is $514,300.00 increase; contract price increases from $13,117,301.55 to $13,131,601.55 as stated in Change Order No. 5.
How much is the S & L Underground contract with City of Thompson Falls worth?
The S & L Underground contract with City of Thompson Falls is valued at $514,300.00 increase; contract price increases from $13,117,301.55 to $13,131,601.55 as stated in Change Order No. 5, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Thompson Falls Report Summary of encroachment complaint in Mountain View Townsite 2026-11-05 (Report), dated November 5, 2026 from City of Thompson Falls. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does S & L Underground hold?
S & L Underground may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Thompson Falls currently buying?
Explore City of Thompson Falls's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.