Stormwater Outfall Construction Bid to J Miller Construction
- Disclosed value
- $646,371.46 plus a 10% contingency in the amount of $64,637.15 for a total amount of $711,008.61
- From agenda
- Document date
- Sep 24, 2020
The 30-second brief
The Pensacola City Council agenda recommends awarding Bid #20-058 for the Alcaniz Street Outfall to Pensacola Bay Stormwater Treatment Enhancement Project to J Miller Construction for a total of $711,008.61 including contingency. The Mayor would be authorized to execute the construction contract and take all actions necessary to complete the stormwater project.
J Miller Construction holds this construction contract with City of Pensacola. Its other public contracts on record include work for Town of Wolcott and Escambia County School District.
Term as filed: Not specified; for duration needed to complete Alcaniz Street Outfall to Pensacola Bay Stormwater Treatment Enhancement Project.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $646,371.46 plus a 10% contingency in the amount of $64,637.15 for a total amount of $711,008.61
- Document date
- September 24, 2020
- Term
- Not specified; for duration needed to complete Alcaniz Street Outfall to Pensacola Bay Stormwater Treatment Enhancement Project
- Vendor
- J Miller Construction
- Agency
- City of Pensacola
- Source document
- city_council_agenda_final_september_24_2020.pdf (Agenda)
J Miller Construction's other public contracts
More City of Pensacola contracts
Questions about this contract
Who was awarded the construction contract by City of Pensacola?
J Miller Construction was awarded this construction contract by City of Pensacola, as recorded on September 24, 2020. The contract value is $646,371.46 plus a 10% contingency in the amount of $64,637.15 for a total amount of $711,008.61.
How much is the J Miller Construction contract with City of Pensacola worth?
The J Miller Construction contract with City of Pensacola is valued at $646,371.46 plus a 10% contingency in the amount of $64,637.15 for a total amount of $711,008.61, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in city_council_agenda_final_september_24_2020.pdf (Agenda), dated September 24, 2020 from City of Pensacola. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does J Miller Construction hold?
J Miller Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Pensacola currently buying?
Explore City of Pensacola's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.