DCR Partners on Hammond Pond Parkway Improvements
- Document date
- Aug 3, 2026
- Term
- Week of August 3–7, 2026
The 30-second brief
The Massachusetts Department of Conservation and Recreation (DCR) is partnering with Newton DPW on Hammond Pond Parkway roadway rehabilitation and intersection improvements scheduled for August 3–7, 2026. Work includes corridor and intersection upgrades between Boylston and Beacon.
DCR holds this construction contract with City of Newton. Its other public contracts on record include work for Glenville State College and Town of Arlington.
Term as filed: Week of August 3–7, 2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- August 3, 2026
- Term
- Week of August 3–7, 2026
- Vendor
- DCR
- Agency
- City of Newton
- Source document
- City of Newton DPW Weekly Construction Schedule 2026-08-03 (Report)
DCR's other public contracts
More City of Newton contracts
Questions about this contract
Who was awarded the construction contract by City of Newton?
DCR was awarded this construction contract by City of Newton, as recorded on August 3, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in City of Newton DPW Weekly Construction Schedule 2026-08-03 (Report), dated August 3, 2026 from City of Newton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does DCR hold?
DCR may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of Newton currently buying?
Explore City of Newton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.