CONTRACTRECOMMENDED

Final Paving Payment Recommended for Valley Paving

City of Jordan
Disclosed value
$16,423.44 final pay request; $1,642,344.21 final construction cost; original contract amount including approved change orders was $1,780,942.59
From report
Document date
Nov 7, 2026
Renews
Free account

The 30-second brief

What it covers

The City of Jordan recommended a $16,423.44 final payment to Valley Paving for the 190th Street and Parking Lot Improvements Project. The final construction cost is $1,642,344.21, with approximately one year remaining in the warranty period.

Who holds it

Valley Paving holds this construction contract with City of Jordan. Its other public contracts on record include work for City of Carver.

What happens next

The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.

Renewal date on recordLocked

Get pre-RFPs for work like this before the bid is out.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$16,423.44 final pay request; $1,642,344.21 final construction cost; original contract amount including approved change orders was $1,780,942.59
Document date
November 7, 2026
Term
Final Pay Request No. 7; work completed through July 2, 2026; approximately 1 year remaining in warranty period
Renews
On record
Source document
City of Jordan Report Final Pay Request 190th Street & Parking Lot Improvements 2026-11-09 (Report)

Valley Paving's other public contracts

More City of Jordan contracts

Questions about this contract

Who was awarded the construction contract by City of Jordan?

Valley Paving was awarded this construction contract by City of Jordan, as recorded on November 7, 2026. The contract value is $16,423.44 final pay request; $1,642,344.21 final construction cost; original contract amount including approved change orders was $1,780,942.59.

How much is the Valley Paving contract with City of Jordan worth?

The Valley Paving contract with City of Jordan is valued at $16,423.44 final pay request; $1,642,344.21 final construction cost; original contract amount including approved change orders was $1,780,942.59, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in City of Jordan Report Final Pay Request 190th Street & Parking Lot Improvements 2026-11-09 (Report), dated November 7, 2026 from City of Jordan. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Valley Paving hold?

Valley Paving may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Jordan currently buying?

Explore City of Jordan's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.