Johnston Approves Trail Construction Change Order for Concrete Connection
- Disclosed value
- Change Order 3: DEDUCT $3,325.00; contract amount to date: $802,630.30; original contract amount: $815,395.50
- From contract
- Document date
- Aug 4, 2026
The 30-second brief
The City of Johnston processed Change Order 3 with Concrete Connection, LLC for the Merle Hay Water Access Trail project. The change order deducts $3,325.00, reducing the contract amount to date to $802,630.30.
Concrete Connection LLC holds this construction contract with City of Johnston. Its other public contracts on record include work for City of Creston and City of Waukee.
See every contract and contact at City of Johnston.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change Order 3: DEDUCT $3,325.00; contract amount to date: $802,630.30; original contract amount: $815,395.50
- Document date
- August 4, 2026
- Vendor
- Concrete Connection LLC
- Agency
- City of Johnston
- Source document
- City of Johnston Contract Change Order 3 Merle Hay Water Access Trail 2026-08-04 (Contract)
Concrete Connection LLC's other public contracts
More City of Johnston contracts
Questions about this contract
Who was awarded the construction contract by City of Johnston?
Concrete Connection LLC was awarded this construction contract by City of Johnston, as recorded on August 4, 2026. The contract value is Change Order 3: DEDUCT $3,325.00; contract amount to date: $802,630.30; original contract amount: $815,395.50.
How much is the Concrete Connection LLC contract with City of Johnston worth?
The Concrete Connection LLC contract with City of Johnston is valued at Change Order 3: DEDUCT $3,325.00; contract amount to date: $802,630.30; original contract amount: $815,395.50, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in City of Johnston Contract Change Order 3 Merle Hay Water Access Trail 2026-08-04 (Contract), dated August 4, 2026 from City of Johnston. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Concrete Connection LLC hold?
Concrete Connection LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Johnston currently buying?
Explore City of Johnston's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.