CONSTRUCTIONAMENDED

Wastewater Contract Amended for Nabholz/Brother's

The City of Elkins approved Change Order No. 4 with Nabholz DBA Brother's Construction for the Wastewater Collection System Improvements Phase I project. The amendment reduces the contract by $50,000 to a new total of $7,094,886.10 and extends the completion date by 12 days to July 20, 2026.

Document date · May 26, 2026

Track City of Elkins contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Elkins.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
New Contract Amount: $7,094,886.10; Change Order: ($50,000.00)
Contract type
CONSTRUCTION
Contract term
Original contract time 400 calendar days; extended 12 days; new completion date July 20, 2026
Renewal date
2026-07-20
Renewal
Change Order No. 4 adjusts both the contract amount and time; new completion date set at 2026-07-20 with an additional 12 days beyond the original 400-day term and prior changes.
Document type
Resolution
Source document
City of Elkins Resolution Acceptance of Low Bid for Van Hoose Valve Vault Improvements Project 2026-05-26

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Elkins?

Nabholz Dba Brother's Construction was awarded this construction contract by City of Elkins, as recorded on May 26, 2026. The contract value is New Contract Amount: $7,094,886.10; Change Order: ($50,000.00).

How much is the Nabholz Dba Brother's Construction contract with City of Elkins worth?

The Nabholz Dba Brother's Construction contract with City of Elkins is valued at New Contract Amount: $7,094,886.10; Change Order: ($50,000.00), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a resolution record.

Where was this contract approved?

This contract appears in City of Elkins Resolution Acceptance of Low Bid for Van Hoose Valve Vault Improvements Project 2026-05-26 (Resolution), dated May 26, 2026 from City of Elkins. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Nabholz Dba Brother's Construction hold?

Nabholz Dba Brother's Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Nabholz Dba Brother's Construction's profile

What is City of Elkins currently buying?

Explore City of Elkins's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Elkins's profile