Wastewater Contract Amended for Nabholz/Brother's
- Disclosed value
- New Contract Amount: $7,094,886.10; Change Order: ($50,000.00)
- From resolution
- Document date
- May 26, 2026
The 30-second brief
The City of Elkins approved Change Order No. 4 with Nabholz DBA Brother's Construction for the Wastewater Collection System Improvements Phase I project. The amendment reduces the contract by $50,000 to a new total of $7,094,886.10 and extends the completion date by 12 days to July 20, 2026.
Nabholz Dba Brother's Construction holds this construction contract with City of Elkins.
Term as filed: Original contract time 400 calendar days; extended 12 days; new completion date July 20, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- New Contract Amount: $7,094,886.10; Change Order: ($50,000.00)
- Document date
- May 26, 2026
- Term
- Original contract time 400 calendar days; extended 12 days; new completion date July 20, 2026
- Vendor
- Nabholz Dba Brother's Construction
- Agency
- City of Elkins
- Source document
- City of Elkins Resolution Acceptance of Low Bid for Van Hoose Valve Vault Improvements Project 2026-05-26 (Resolution)
More City of Elkins contracts
Questions about this contract
Who was awarded the construction contract by City of Elkins?
Nabholz Dba Brother's Construction was awarded this construction contract by City of Elkins, as recorded on May 26, 2026. The contract value is New Contract Amount: $7,094,886.10; Change Order: ($50,000.00).
How much is the Nabholz Dba Brother's Construction contract with City of Elkins worth?
The Nabholz Dba Brother's Construction contract with City of Elkins is valued at New Contract Amount: $7,094,886.10; Change Order: ($50,000.00), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a resolution record.
Where was this contract approved?
This contract appears in City of Elkins Resolution Acceptance of Low Bid for Van Hoose Valve Vault Improvements Project 2026-05-26 (Resolution), dated May 26, 2026 from City of Elkins. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is City of Elkins currently buying?
Explore City of Elkins's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.