CONTRACTONGOING

Mittauer assists Cedar Key with ramp feasibility study

City of Cedar Key
Disclosed value
$249,000 FBIP grant-funded feasibility and design study; total project cost $256,626; FBIP amount requested $249,500
From agenda
Document date
Aug 11, 2026

The 30-second brief

What it covers

The City of Cedar Key is utilizing Mittauer & Associates, Inc. in partnership with CPH Consulting, LLC to provide FBIP grant-funded engineering and consulting services for the outer boat ramp expansion project through June 23, 2026. The engagement supports feasibility analysis, design, and related technical studies for future construction.

Who holds it

Mittauer & Associates Inc holds this professional services contract with City of Cedar Key. Its other public contracts on record include work for City of Crescent and Town of Welaka.

What happens next

Term as filed: Project Goals & Timeline: Surveys complete by 11/6/2025; Environmental Studies complete by 11/29/2025; Geotechnical Investigation complete by 12/14/2025; Project Completion 6/23/2026.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Professional Services
Amount
$249,000 FBIP grant-funded feasibility and design study; total project cost $256,626; FBIP amount requested $249,500
Document date
August 11, 2026
Term
Project Goals & Timeline: Surveys complete by 11/6/2025; Environmental Studies complete by 11/29/2025; Geotechnical Investigation complete by 12/14/2025; Project Completion 6/23/2026
Vendor
Mittauer & Associates Inc
Source document
City of Cedar Key Agenda Boat Ramp Workshop 2026-08-11 (Agenda)

Mittauer & Associates Inc's other public contracts

More City of Cedar Key contracts

Questions about this contract

Who was awarded the professional services contract by City of Cedar Key?

Mittauer & Associates Inc was awarded this professional services contract by City of Cedar Key, as recorded on August 11, 2026. The contract value is $249,000 FBIP grant-funded feasibility and design study; total project cost $256,626; FBIP amount requested $249,500.

How much is the Mittauer & Associates Inc contract with City of Cedar Key worth?

The Mittauer & Associates Inc contract with City of Cedar Key is valued at $249,000 FBIP grant-funded feasibility and design study; total project cost $256,626; FBIP amount requested $249,500, covering professional services work.

What type of contract is this?

This is a Professional Services contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Cedar Key Agenda Boat Ramp Workshop 2026-08-11 (Agenda), dated August 11, 2026 from City of Cedar Key. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is City of Cedar Key currently buying?

Explore City of Cedar Key's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.