Calexico Recommends $12,177 Deduction for Rove Contract
- Disclosed value
- ($12,177.02); total contract amount $1,157,603.98
- From staffreport
- Document date
- Nov 2, 2026
The 30-second brief
Calexico staff recommended authorizing Deductive Change Order No. 2 with Rove Engineering, Inc. for the Alley Improvement Project – Phase III, reducing the contract by $12,177.02. The adjustment reconciles final construction quantities and billing, resulting in a total contract value of $1,157,603.98.
Rove Engineering Inc holds this construction contract with City of Calexico. Its other public contracts on record include work for City of Westmorland.
Term as filed: Approved November 4, 2026; project end date not stated.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- ($12,177.02); total contract amount $1,157,603.98
- Document date
- November 2, 2026
- Term
- Approved November 4, 2026; project end date not stated
- Vendor
- Rove Engineering Inc
- Agency
- City of Calexico
- Source document
- Calexico Staff Report Deductive Change Order No. 2 for Alley Improvement Project Phase III 2026-11-04 (StaffReport)
Rove Engineering Inc's other public contracts
More City of Calexico contracts
Questions about this contract
Who was awarded the construction contract by City of Calexico?
Rove Engineering Inc was awarded this construction contract by City of Calexico, as recorded on November 2, 2026. The contract value is ($12,177.02); total contract amount $1,157,603.98.
How much is the Rove Engineering Inc contract with City of Calexico worth?
The Rove Engineering Inc contract with City of Calexico is valued at ($12,177.02); total contract amount $1,157,603.98, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Calexico Staff Report Deductive Change Order No. 2 for Alley Improvement Project Phase III 2026-11-04 (StaffReport), dated November 2, 2026 from City of Calexico. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Rove Engineering Inc hold?
Rove Engineering Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Calexico currently buying?
Explore City of Calexico's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.