CONTRACTAMENDED

Calexico Recommends $12,177 Deduction for Rove Contract

City of Calexico logoCity of Calexico
Disclosed value
($12,177.02); total contract amount $1,157,603.98
From staffreport
Document date
Nov 2, 2026

The 30-second brief

What it covers

Calexico staff recommended authorizing Deductive Change Order No. 2 with Rove Engineering, Inc. for the Alley Improvement Project – Phase III, reducing the contract by $12,177.02. The adjustment reconciles final construction quantities and billing, resulting in a total contract value of $1,157,603.98.

Who holds it

Rove Engineering Inc holds this construction contract with City of Calexico. Its other public contracts on record include work for City of Westmorland.

What happens next

Term as filed: Approved November 4, 2026; project end date not stated.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
($12,177.02); total contract amount $1,157,603.98
Document date
November 2, 2026
Term
Approved November 4, 2026; project end date not stated
Source document
Calexico Staff Report Deductive Change Order No. 2 for Alley Improvement Project Phase III 2026-11-04 (StaffReport)

Rove Engineering Inc's other public contracts

More City of Calexico contracts

Questions about this contract

Who was awarded the construction contract by City of Calexico?

Rove Engineering Inc was awarded this construction contract by City of Calexico, as recorded on November 2, 2026. The contract value is ($12,177.02); total contract amount $1,157,603.98.

How much is the Rove Engineering Inc contract with City of Calexico worth?

The Rove Engineering Inc contract with City of Calexico is valued at ($12,177.02); total contract amount $1,157,603.98, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Calexico Staff Report Deductive Change Order No. 2 for Alley Improvement Project Phase III 2026-11-04 (StaffReport), dated November 2, 2026 from City of Calexico. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Rove Engineering Inc hold?

Rove Engineering Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Calexico currently buying?

Explore City of Calexico's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →