Burlingame Plans Tank Rehabilitation Change Order
- Disclosed value
- $68,000 change order and $10,200 additional 15% contingency; increased total not-to-exceed contract amount of $353,855
- From agenda
- Document date
- Oct 19, 2026
The 30-second brief
Burlingame plans to authorize a $68,000 change order with SoCal Pacific Construction Corp. dba National Coating and Lining for rehabilitation of the Donnelly and Alcazar tanks. A $10,200 contingency would raise the total not-to-exceed contract amount to $353,855.
Socal Pacific Construction Corp Dba National Coating & Lining holds this construction contract with City of Burlingame. Its other public contracts on record include work for Sacramento County and Inland Empire Utilities Agency.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $68,000 change order and $10,200 additional 15% contingency; increased total not-to-exceed contract amount of $353,855
- Document date
- October 19, 2026
- Vendor
- Socal Pacific Construction Corp Dba National Coating & Lining
- Agency
- City of Burlingame
- Source document
- City of Burlingame Agenda City Council Meeting October 19, 2026 (Agenda)
Socal Pacific Construction Corp Dba National Coating & Lining's other public contracts
More City of Burlingame contracts
Questions about this contract
Who was awarded the construction contract by City of Burlingame?
Socal Pacific Construction Corp Dba National Coating & Lining was awarded this construction contract by City of Burlingame, as recorded on October 19, 2026. The contract value is $68,000 change order and $10,200 additional 15% contingency; increased total not-to-exceed contract amount of $353,855.
How much is the Socal Pacific Construction Corp Dba National Coating & Lining contract with City of Burlingame worth?
The Socal Pacific Construction Corp Dba National Coating & Lining contract with City of Burlingame is valued at $68,000 change order and $10,200 additional 15% contingency; increased total not-to-exceed contract amount of $353,855, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in City of Burlingame Agenda City Council Meeting October 19, 2026 (Agenda), dated October 19, 2026 from City of Burlingame. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is City of Burlingame currently buying?
Explore City of Burlingame's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.