Southwest Steel Continues Area C Steel Work
- Document date
- Oct 19, 2026
- Term
- Ongoing; work reported October 19, 2026
The 30-second brief
Southwest Steel continued structural-steel work at the One Beverly Hills Project. The company performed steel erection and welding in area C.
Southwest Steel holds this construction contract with City of Beverly Hills. Its other public contracts on record include work for Town of Rico.
Term as filed: Ongoing; work reported October 19, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- October 19, 2026
- Term
- Ongoing; work reported October 19, 2026
- Vendor
- Southwest Steel
- Agency
- City of Beverly Hills
- Source document
- City of Beverly Hills Report One Beverly Hills Project Daily Construction Monitor Report 2026-10-19 (Report)
Southwest Steel's other public contracts
More City of Beverly Hills contracts
Questions about this contract
Who was awarded the construction contract by City of Beverly Hills?
Southwest Steel was awarded this construction contract by City of Beverly Hills, as recorded on October 19, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in City of Beverly Hills Report One Beverly Hills Project Daily Construction Monitor Report 2026-10-19 (Report), dated October 19, 2026 from City of Beverly Hills. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Southwest Steel hold?
Southwest Steel may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of Beverly Hills currently buying?
Explore City of Beverly Hills's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.