CONTRACTAMENDED

Advance Construction Stormwater Contract Nears Final Payment

City of Appleton logoCity of Appleton
Disclosed value
Original award of $119,802.75 with a $11,980.27 contingency; approved change orders totaling $11,963.59; final contract amount of $131,766.34 with $0 contingency; final payment of $6,588.32
From agenda
Document date
Oct 26, 2026

The 30-second brief

What it covers

The City of Appleton reports that Advance Construction, Inc. completed the G-26 Stormwater Pond Dredging contract. Approved change orders brought the final contract amount to $131,766.34, and the city is requesting the remaining $6,588.32 final payment.

Who holds it

Advance Construction Inc holds this construction contract with City of Appleton. Its other public contracts on record include work for Howard village and Kimberly village.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Original award of $119,802.75 with a $11,980.27 contingency; approved change orders totaling $11,963.59; final contract amount of $131,766.34 with $0 contingency; final payment of $6,588.32
Document date
October 26, 2026
Source document
City of Appleton Agenda Finance Committee Meeting, October 26, 2026 (Agenda)

Advance Construction Inc's other public contracts

More City of Appleton contracts

Questions about this contract

Who was awarded the construction contract by City of Appleton?

Advance Construction Inc was awarded this construction contract by City of Appleton, as recorded on October 26, 2026. The contract value is Original award of $119,802.75 with a $11,980.27 contingency; approved change orders totaling $11,963.59; final contract amount of $131,766.34 with $0 contingency; final payment of $6,588.32.

How much is the Advance Construction Inc contract with City of Appleton worth?

The Advance Construction Inc contract with City of Appleton is valued at Original award of $119,802.75 with a $11,980.27 contingency; approved change orders totaling $11,963.59; final contract amount of $131,766.34 with $0 contingency; final payment of $6,588.32, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Appleton Agenda Finance Committee Meeting, October 26, 2026 (Agenda), dated October 26, 2026 from City of Appleton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Advance Construction Inc hold?

Advance Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Appleton currently buying?

Explore City of Appleton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →