Mancini Capital Project Contract Increased by Change Order
- Disclosed value
- Increase of $17,869.24 (new total $10,308,940.76)
- From minutes
- Document date
- Jun 4, 2026
The 30-second brief
The Board approved a change order for Andrew R. Mancini Associates, Inc., increasing its May 2019 capital project contract by $17,869.24 to a new total of $10,308,940.76. The action also utilizes the remaining $4,739.00 in contractual allowance.
Andrew R. Mancini Associates Inc holds this construction contract with Chenango Forks Central School District. Its other public contracts on record include work for Union-Endicott Central School District and Maine-Endwell Central School District.
See every contract and contact at Chenango Forks Central School District.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of $17,869.24 (new total $10,308,940.76)
- Document date
- June 4, 2026
- Source document
- Chenango Forks Central School District Minutes Regular Board of Education Meeting 2026-06-04 (Minutes)
Andrew R. Mancini Associates Inc's other public contracts
More Chenango Forks Central School District contracts
Questions about this contract
Who was awarded the construction contract by Chenango Forks Central School District?
Andrew R. Mancini Associates Inc was awarded this construction contract by Chenango Forks Central School District, as recorded on June 4, 2026. The contract value is Increase of $17,869.24 (new total $10,308,940.76).
How much is the Andrew R. Mancini Associates Inc contract with Chenango Forks Central School District worth?
The Andrew R. Mancini Associates Inc contract with Chenango Forks Central School District is valued at Increase of $17,869.24 (new total $10,308,940.76), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Chenango Forks Central School District Minutes Regular Board of Education Meeting 2026-06-04 (Minutes), dated June 4, 2026 from Chenango Forks Central School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Andrew R. Mancini Associates Inc hold?
Andrew R. Mancini Associates Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Chenango Forks Central School District currently buying?
Explore Chenango Forks Central School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.