CONTRACTRECOMMENDED

Village Selects Contingent Bidder For Water Main Project

Malcolm village
Disclosed value
Estimated total project cost $451,000, with $110,000 allocated to the Fire Department phase
From minutes
Document date
Apr 6, 2026

The 30-second brief

What it covers

The Village of Malcolm Board of Trustees voted to accept Wright Sewer & Water LLC as the bidder for the Water Main Project, contingent on reference verification and bidder responsibility, with an estimated cost of $451,000 and completion by August 7, 2026. The project prioritizes a $110,000 Fire Department phase, with split payments in April 2026 and upon completion.

Who holds it

Wright Sewer & Water LLC holds this construction contract with Malcolm village. Its other public contracts on record include work for City of Gretna and Eagle village.

What happens next

Term as filed: Project completion estimated by August 7, 2026; Fire Department phase paid 50% in April 2026 and 50% upon completion.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Estimated total project cost $451,000, with $110,000 allocated to the Fire Department phase
Document date
April 6, 2026
Term
Project completion estimated by August 7, 2026; Fire Department phase paid 50% in April 2026 and 50% upon completion
Vendor
Wright Sewer & Water LLC
Source document
Village of Malcolm Board of Trustees Meeting Minutes 2026-04-06 (Minutes)

Wright Sewer & Water LLC's other public contracts

More Malcolm village contracts

Questions about this contract

Who was awarded the construction contract by Malcolm village?

Wright Sewer & Water LLC was awarded this construction contract by Malcolm village, as recorded on April 6, 2026. The contract value is Estimated total project cost $451,000, with $110,000 allocated to the Fire Department phase.

How much is the Wright Sewer & Water LLC contract with Malcolm village worth?

The Wright Sewer & Water LLC contract with Malcolm village is valued at Estimated total project cost $451,000, with $110,000 allocated to the Fire Department phase, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Village of Malcolm Board of Trustees Meeting Minutes 2026-04-06 (Minutes), dated April 6, 2026 from Malcolm village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is Malcolm village currently buying?

Explore Malcolm village's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →