village_of_eagle_board_of_trustees_meeting_minutes.pdf

Payment No. 2 Considered for 6th Street Water Main

$13,050.42Eagle villageWRIGHT SEWER & WATER LLCSeptember 15, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Village of Eagle considered approval of Application for Payment No. 2 to Wright Sewer & Water, LLC for $13,050.42 on the 6th Street Water Main Extension Project. The payment reflects additional work under a contract now totaling $156,508.45 after change orders.

Contract Details

Contract Amount

$13,050.42

Vendor

WRIGHT SEWER & WATER LLC

Agency

Eagle village, NE

Contract Type

CONSTRUCTION

Document Date

September 15, 2025

Contract Term

Original contract date June 4, 2024; original time 59 days plus 7 days added by change order (total 66 days)

Renewal Info

Original contract amount $149,723.60 with a net change order increase of $6,784.85, bringing the total contract to $156,508.45 and extending contract time from 59 to 66 days. All contract time has been used, indicating substantial completion.