AA Meyers Advances ARPA Water Line Upgrade Project
Calcasieu Waterworks District 9 Ward 4Utility District · Sulphur, LA- Document date
- Apr 13, 2026
The 30-second brief
AA Meyers is advancing Waterworks District 9’s ARPA-funded 2023 Water Line Upgrade Project. The contractor has installed the new water lines, fire hydrants and service saddles on AA Meyers Road and is targeting completion in April 2026.
Aa Meyers holds this construction contract with Calcasieu Waterworks District 9 Ward 4.
Term as filed: 365 calendar days, amended to 386 calendar days; estimated completion April 28, 2026, with contractor schedule anticipating April 22, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- April 13, 2026
- Term
- 365 calendar days, amended to 386 calendar days; estimated completion April 28, 2026, with contractor schedule anticipating April 22, 2026
- Vendor
- Aa Meyers
- Source document
- Waterworks District 9 Ward 4 Minutes Regular Meeting 2026-04-13 (Minutes)
More Calcasieu Waterworks District 9 Ward 4 contracts
Questions about this contract
Who was awarded the construction contract by Calcasieu Waterworks District 9 Ward 4?
Aa Meyers was awarded this construction contract by Calcasieu Waterworks District 9 Ward 4, as recorded on April 13, 2026.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Waterworks District 9 Ward 4 Minutes Regular Meeting 2026-04-13 (Minutes), dated April 13, 2026 from Calcasieu Waterworks District 9 Ward 4. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What is Calcasieu Waterworks District 9 Ward 4 currently buying?
Explore Calcasieu Waterworks District 9 Ward 4's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.