City Approves Change Order for 56th Street Stormwater Project
- Disclosed value
- Change order increase $166,665.34; net of $328,743 in savings and $495,408 in added costs
- From agendapacket
- Document date
- May 26, 2026
The 30-second brief
Holmes Beach amended its Resilient Florida Stormwater Improvements construction contract with Harris-McBurney Company, approving a $166,665.34 net increase to address unforeseen conflicts with County utilities along 56th Street. The change order reconfigures the stormwater main to reduce utility conflicts and uses existing grant and paving funds to cover the additional cost.
Harris-mcburney Company holds this construction contract with City of Holmes Beach. Its other public contracts on record include work for City of Tampa and City of Avon Park.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change order increase $166,665.34; net of $328,743 in savings and $495,408 in added costs
- Document date
- May 26, 2026
- Vendor
- Harris-mcburney Company
- Agency
- City of Holmes Beach
- Source document
- City of Holmes Beach AgendaPacket 2026-05-26 (AgendaPacket)
Harris-mcburney Company's other public contracts
More City of Holmes Beach contracts
Questions about this contract
Who was awarded the construction contract by City of Holmes Beach?
Harris-mcburney Company was awarded this construction contract by City of Holmes Beach, as recorded on May 26, 2026. The contract value is Change order increase $166,665.34; net of $328,743 in savings and $495,408 in added costs.
How much is the Harris-mcburney Company contract with City of Holmes Beach worth?
The Harris-mcburney Company contract with City of Holmes Beach is valued at Change order increase $166,665.34; net of $328,743 in savings and $495,408 in added costs, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in City of Holmes Beach AgendaPacket 2026-05-26 (AgendaPacket), dated May 26, 2026 from City of Holmes Beach. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Harris-mcburney Company hold?
Harris-mcburney Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Holmes Beach currently buying?
Explore City of Holmes Beach's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.