Port Seeks Fourth Change Order for Pier B Rail Yard
Trusted by teams at
Description
The Port of Long Beach proposes Change Order No. 4 to its construction contract with Stacy Witbeck, Inc. for the Pier B Rail Yard East Expansion, adding $769,724.27 in net cost and extending substantial completion to February 19, 2027. The amendment covers additional earthwork, hazardous waste disposal, pile casing, and overhead associated with resolving unforeseen field conditions.
Contract Details
Contract Amount
$769,724.27 (Change Order No. 4); revised total contract amount $24,687,348.69 (original $21,730,336 plus Change Orders 1–4 totaling $2,957,012.69)
Vendor
STACY WITBECK INC
Agency
Port of Long Beach, CA
Contract Type
CONSTRUCTION
Document Date
May 11, 2026
Contract Term
Notice-to-Proceed August 26, 2024; revised Substantial Completion date February 19, 2027; revised Affidavit of Final Completion date May 20, 2027
Renewal Date
2027-05-20
Renewal Info
Change Order No. 4 amends Contract HD-24-0058 by increasing compensation by $769,724.27 and extending milestones 5–7, including Substantial and Final Completion, by 176 calendar days (133 compensable, 43 non-compensable). Prior Board actions ratified or authorized Change Orders 1–3 totaling $2,187,288.42, for cumulative change orders of $2,957,012.69 and a 13.61% contract increase.
More from STACY WITBECK INC
More from Port of Long Beach
Port of Long Beach Board of Harbor Commissioners Meeting Agenda May 11 2026
Port of Long Beach Board of Harbor Commissioners Meeting Agenda May 11 2026
Port of Long Beach Board of Harbor Commissioners Meeting Agenda May 11 2026
Port of Long Beach Board of Harbor Commissioners Meeting Agenda May 11 2026
Port of Long Beach Staff Report File HD-26-214 2026-05-11
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.