Jail Renovation Construction Continues With English Construction
Albemarle-Charlottesville Regional JailPublic Authority · Charlottesville, VA- Disclosed value
- $40,105,160 total construction budget; $6,971,619 spent through May 31, 2026; $9,522,153 spent through August 31, 2026
- From agendapacket
- Document date
- Sep 10, 2026
- Renews
- Free account
The 30-second brief
Albemarle-Charlottesville Regional Jail Authority continues its renovation construction contract with English Construction. The project has a $40.1 million construction budget and is scheduled for substantial completion on December 24, 2027.
English Construction holds this construction contract with Albemarle-Charlottesville Regional Jail. Its other public contracts on record include work for Rivanna Water and Sewer Authority and Nottoway County.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $40,105,160 total construction budget; $6,971,619 spent through May 31, 2026; $9,522,153 spent through August 31, 2026
- Document date
- September 10, 2026
- Term
- September 15, 2025 – December 24, 2027 substantial completion
- Renews
- On record
- Vendor
- English Construction
- Source document
- Albemarle-Charlottesville Regional Jail Authority AgendaPacket Board Business Meeting 2026-09-10 (AgendaPacket)
English Construction's other public contracts
More Albemarle-Charlottesville Regional Jail contracts
Questions about this contract
Who was awarded the construction contract by Albemarle-Charlottesville Regional Jail?
English Construction was awarded this construction contract by Albemarle-Charlottesville Regional Jail, as recorded on September 10, 2026. The contract value is $40,105,160 total construction budget; $6,971,619 spent through May 31, 2026; $9,522,153 spent through August 31, 2026.
How much is the English Construction contract with Albemarle-Charlottesville Regional Jail worth?
The English Construction contract with Albemarle-Charlottesville Regional Jail is valued at $40,105,160 total construction budget; $6,971,619 spent through May 31, 2026; $9,522,153 spent through August 31, 2026, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Albemarle-Charlottesville Regional Jail Authority AgendaPacket Board Business Meeting 2026-09-10 (AgendaPacket), dated September 10, 2026 from Albemarle-Charlottesville Regional Jail. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does English Construction hold?
English Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Albemarle-Charlottesville Regional Jail currently buying?
Explore Albemarle-Charlottesville Regional Jail's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.