Plumbing Construction Contract Reported for School Project
- Disclosed value
- Original award $4,766,500.00; final cost with change orders $4,967,345.00; expended to date $4,967,345.00
- From report
- Document date
- Oct 1, 2026
- Term
- November 28, 2018 – September 1, 2022
The 30-second brief
The agency reported Jay R. Reynolds, Inc. for plumbing construction work. The contract had an adjusted final cost of $4,967,345.00 and was fully expended by the reported completion date.
Jay R. Reynolds Inc holds this construction contract with Abington SD. Its other public contracts on record include work for Cornwall-Lebanon SD and Upper Darby SD.
Term as filed: November 28, 2018 – September 1, 2022.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Original award $4,766,500.00; final cost with change orders $4,967,345.00; expended to date $4,967,345.00
- Document date
- October 1, 2026
- Term
- November 28, 2018 – September 1, 2022
- Vendor
- Jay R. Reynolds Inc
- Agency
- Abington SD
- Source document
- Capital Improvement Report Capital Improvement Report October 2026 2026-10-01 (Report)
Jay R. Reynolds Inc's other public contracts
More Abington SD contracts
Questions about this contract
Who was awarded the construction contract by Abington SD?
Jay R. Reynolds Inc was awarded this construction contract by Abington SD, as recorded on October 1, 2026. The contract value is Original award $4,766,500.00; final cost with change orders $4,967,345.00; expended to date $4,967,345.00.
How much is the Jay R. Reynolds Inc contract with Abington SD worth?
The Jay R. Reynolds Inc contract with Abington SD is valued at Original award $4,766,500.00; final cost with change orders $4,967,345.00; expended to date $4,967,345.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Capital Improvement Report Capital Improvement Report October 2026 2026-10-01 (Report), dated October 1, 2026 from Abington SD. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Jay R. Reynolds Inc hold?
Jay R. Reynolds Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Abington SD currently buying?
Explore Abington SD's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.