CONTRACTDISCUSSED

Architect Selected for PSU Stadium End Zone Facility

Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas logoKansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas
Disclosed value
$1,100,000 (design fees within $14,000,000 project budget)
From agendapacket
Document date
May 5, 2026

The 30-second brief

What it covers

Pittsburg State University engaged Hollis + Miller Architects to prepare the program and budget for a $14 million North End Zone Facility at Carnie Smith Stadium, funded entirely by private gifts. The project is planned as a single-phase design-build effort with construction centered around late 2027.

Who holds it

Hollis + Miller Architects holds this professional services contract with Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas. Its other public contracts on record include work for Johnson County Community College and Park Hill School District.

What happens next

Term as filed: Design through construction for single-phase project with construction midpoint December 2027.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Professional Services
Amount
$1,100,000 (design fees within $14,000,000 project budget)
Document date
May 5, 2026
Term
Design through construction for single-phase project with construction midpoint December 2027
Source document
Kansas Board of Regents Fiscal Affairs and Audit Standing Committee Agenda Planning Meeting 2026-05-05 (AgendaPacket)

Hollis + Miller Architects's other public contracts

More Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas contracts

Questions about this contract

Who was awarded the professional services contract by Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas?

Hollis + Miller Architects was awarded this professional services contract by Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas, as recorded on May 5, 2026. The contract value is $1,100,000 (design fees within $14,000,000 project budget).

How much is the Hollis + Miller Architects contract with Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas worth?

The Hollis + Miller Architects contract with Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas is valued at $1,100,000 (design fees within $14,000,000 project budget), covering professional services work.

What type of contract is this?

This is a Professional Services contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Kansas Board of Regents Fiscal Affairs and Audit Standing Committee Agenda Planning Meeting 2026-05-05 (AgendaPacket), dated May 5, 2026 from Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Hollis + Miller Architects hold?

Hollis + Miller Architects may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas currently buying?

Explore Kansas Board of Regents Fiscal Affairs and Audit Standing Committee | State of Kansas's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →