Johnson Controls solar project facing delays
- Document date
- Apr 28, 2025
The 30-second brief
Johnson Controls facing slight delays in solar project at the train station due to part procurement issues, delaying charging station installation as well; Verizon fiberoptic line adds extra cost.
Johnson Controls Inc. holds this energy efficiency contract with Village of Patchogue CDA. Its other public contracts on record include work for Trenton Special School District and Dolton SD 149.
See every contract and contact at Village of Patchogue CDA.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Energy Efficiency
- Document date
- April 28, 2025
- Term
- NA
- Vendor
- Johnson Controls Inc.
- Agency
- Village of Patchogue CDA
- Source document
- village-of-patchogue-cda-meeting-minutes-2025-04-28_8d9.pdf (Meeting Minutes)
Johnson Controls Inc.'s other public contracts
More Village of Patchogue CDA contracts
Questions about this contract
Who was awarded the energy efficiency contract by Village of Patchogue CDA?
Johnson Controls Inc. was awarded this energy efficiency contract by Village of Patchogue CDA, as recorded on April 28, 2025.
What type of contract is this?
This is a Energy Efficiency contract, documented as a meeting minutes record.
Where was this contract approved?
This contract appears in village-of-patchogue-cda-meeting-minutes-2025-04-28_8d9.pdf (Meeting Minutes), dated April 28, 2025 from Village of Patchogue CDA. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Johnson Controls Inc. hold?
Johnson Controls Inc. may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Village of Patchogue CDA currently buying?
Explore Village of Patchogue CDA's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.