Stateline Continues FM 1385 Road Rehabilitation

Denton County logoDenton County
Document date
Mar 1, 2026

The 30-second brief

What it covers

Stateline is performing construction under TxDOT Project F 2023(171) to rehabilitate FM 1385 between FM 428 and FM 455, focusing on asphalt pavement and final striping through April 2026.

Who holds it

STATELINE holds this construction contract with Denton County. Its other public contracts on record include work for Town of Thetford and Port Of Waterman.

What happens next

Term as filed: Work began March 17, 2025; anticipated completion April 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
March 1, 2026
Term
Work began March 17, 2025; anticipated completion April 2026
Vendor
STATELINE
Source document
Denton County Precinct 1 Transportation Report March 2026 (Report)

STATELINE's other public contracts

More Denton County contracts

Questions about this contract

Who was awarded the construction contract by Denton County?

STATELINE was awarded this construction contract by Denton County, as recorded on March 1, 2026.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Denton County Precinct 1 Transportation Report March 2026 (Report), dated March 1, 2026 from Denton County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does STATELINE hold?

STATELINE may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is Denton County currently buying?

Explore Denton County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →