Board Approves Major Change Orders for Cedro Waterline Project
Trusted by teams at
Description
The Board adopted Resolution 2025/2026-21 ratifying and approving three change orders with Cedro Construction, Inc. for the Water Line Relocation Project, addressing unforeseen asbestos-cement pipe abatement, redesign, and extra testing. These changes add $331,870.32 to the original $716,145.30 contract, bringing the total to $1,048,015.62, fully funded by bond proceeds.
Contract Details
Contract Amount
Original Contract $716,145.30 (including $75,000 allowance); Change Orders 005, 006, 008 add $331,870.32 for new total $1,048,015.62
Vendor
CEDRO CONSTRUCTION INC
Agency
College Of The Canyons, CA
Contract Type
CONSTRUCTION
Document Date
May 13, 2026
Renewal Info
Construction contract amended via Change Orders 005, 006, and 008 to address unforeseen conditions; statutory rebidding deemed unnecessary under California case law.
More from CEDRO CONSTRUCTION INC
More from College Of The Canyons
Santa Clarita Community College District Board Meeting Agenda 2026-05-13
Santa Clarita Community College District Board Meeting Agenda 2026-05-13
Santa Clarita Community College District Board Meeting Agenda 2026-05-13
Santa Clarita Community College District Board Meeting Agenda 2026-05-13
Santa Clarita Community College District Board Meeting Agenda 2026-05-13
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.