CONTRACTAMENDED

Board Approves Major Change Orders for Cedro Waterline Project

College Of The Canyons logoCollege Of The Canyons
Disclosed value
Original Contract $716,145.30 (including $75,000 allowance); Change Orders 005, 006, 008 add $331,870.32 for new total $1,048,015.62
From agenda
Document date
May 13, 2026

The 30-second brief

What it covers

The Board adopted Resolution 2025/2026-21 ratifying and approving three change orders with Cedro Construction, Inc. for the Water Line Relocation Project, addressing unforeseen asbestos-cement pipe abatement, redesign, and extra testing. These changes add $331,870.32 to the original $716,145.30 contract, bringing the total to $1,048,015.62, fully funded by bond proceeds.

Who holds it

Cedro Construction Inc holds this construction contract with College Of The Canyons. Its other public contracts on record include work for City of Fillmore and Santa Clarita Valley Water Agency.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Original Contract $716,145.30 (including $75,000 allowance); Change Orders 005, 006, 008 add $331,870.32 for new total $1,048,015.62
Document date
May 13, 2026
Source document
Santa Clarita Community College District Board Meeting Agenda 2026-05-13 (Agenda)

Cedro Construction Inc's other public contracts

More College Of The Canyons contracts

Questions about this contract

Who was awarded the construction contract by College Of The Canyons?

Cedro Construction Inc was awarded this construction contract by College Of The Canyons, as recorded on May 13, 2026. The contract value is Original Contract $716,145.30 (including $75,000 allowance); Change Orders 005, 006, 008 add $331,870.32 for new total $1,048,015.62.

How much is the Cedro Construction Inc contract with College Of The Canyons worth?

The Cedro Construction Inc contract with College Of The Canyons is valued at Original Contract $716,145.30 (including $75,000 allowance); Change Orders 005, 006, 008 add $331,870.32 for new total $1,048,015.62, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Santa Clarita Community College District Board Meeting Agenda 2026-05-13 (Agenda), dated May 13, 2026 from College Of The Canyons. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Cedro Construction Inc hold?

Cedro Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.