CONTRACTONGOING

Morgan Contracting Advances Utility Construction Projects

City of Johnson logoCity of Johnson
Disclosed value
$278,977.48 (recent Sinking Creek Sewer Pump Station Upgrades payment); $9,274,250 (total for Sinking Creek work); $7,223,051.85 (H Sewer Lift Station Project)
From agenda
Document date
Feb 19, 2026
Renews
Free account

The 30-second brief

What it covers

Morgan Contracting continues major construction on the Sinking Creek and H Sewer Pump Station Upgrade projects, with contract totals exceeding $16 million.

Who holds it

Morgan Contracting holds this construction contract with City of Johnson. Its other public contracts on record include work for City of Huntsville and Johnson city Housing Authority.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every City of Johnson contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$278,977.48 (recent Sinking Creek Sewer Pump Station Upgrades payment); $9,274,250 (total for Sinking Creek work); $7,223,051.85 (H Sewer Lift Station Project)
Document date
February 19, 2026
Term
Through 2027 for Sinking Creek and H Sewer; Sinking Creek construction to complete April 30, 2026
Renews
Free account
Source document
City of Johnson City Commission Meeting Agenda Feb 2026 (Agenda)

Morgan Contracting's other public contracts

More City of Johnson contracts

Questions about this contract

Who was awarded the construction contract by City of Johnson?

Morgan Contracting was awarded this construction contract by City of Johnson, as recorded on February 19, 2026. The contract value is $278,977.48 (recent Sinking Creek Sewer Pump Station Upgrades payment); $9,274,250 (total for Sinking Creek work); $7,223,051.85 (H Sewer Lift Station Project).

How much is the Morgan Contracting contract with City of Johnson worth?

The Morgan Contracting contract with City of Johnson is valued at $278,977.48 (recent Sinking Creek Sewer Pump Station Upgrades payment); $9,274,250 (total for Sinking Creek work); $7,223,051.85 (H Sewer Lift Station Project), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Johnson City Commission Meeting Agenda Feb 2026 (Agenda), dated February 19, 2026 from City of Johnson. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Morgan Contracting hold?

Morgan Contracting may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Johnson currently buying?

Explore City of Johnson's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →