Water wells project contract reduced via Change Order 3
Trusted by teams at
Description
The Edmond Public Works Authority approved Change Order No. 3 with Hydro Resources Mid Continent Inc. for the Water Wells - Phase 1 project, decreasing the contract by $34,713.00. The amendment reconciles field quantities and sets the final contract amount at $8,397,838.58 with no time adjustment.
Contract Details
Contract Amount
$34,713.00 Decrease (revised total $8,397,838.58)
Vendor
HYDRO RESOURCES MID CONTINENT INC
Agency
City of Edmond, OK
Contract Type
CONSTRUCTION
Document Date
November 10, 2025
Renewal Info
Original contract was $9,603,786.31; Change Orders 1 and 2 and liquidated damages previously reduced the contract. Change Order 3 further decreases the amount by $34,713.00 with no additional scope or time changes.
More from HYDRO RESOURCES MID CONTINENT INC
More from City of Edmond
Edmond Economic Development Authority Board Regular Meeting Agenda 2026-06-16
Edmond Economic Development Authority Board Regular Meeting Agenda 2026-06-16
City of Edmond AgendaPacket Visual Arts Commission Meeting 2026-06-16
City of Edmond AgendaPacket Visual Arts Commission Meeting 2026-06-16
City of Edmond AgendaPacket Visual Arts Commission Meeting 2026-06-16
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.