Palmer Plantation Mud 2 Awards Equipment Contract to COHEN (June 2024)
Palmer Plantation Mud 2Utility District · Houston, TX- Awarded
- Jun 19, 2024
- Term
- April 30, 2024 – August 21, 2024
The 30-second brief
Cohen issued purchase order to supply pipe and fittings for Palmer Plantation MUD No. 2 project, with completion by late August 2024.
COHEN holds this equipment contract with Palmer Plantation Mud 2. Its other public contracts on record include work for Princess Pocotopaug Tax District and Town of Starksboro.
Term as filed: April 30, 2024 – August 21, 2024.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Equipment
- Document date
- June 19, 2024
- Term
- April 30, 2024 – August 21, 2024
- Vendor
- COHEN
- Agency
- Palmer Plantation Mud 2
- Source document
- palmer-plantation-mud-no-2-engineering-report-june-19-2024_d85.pdf (Report)
COHEN's other public contracts
More Palmer Plantation Mud 2 contracts
Questions about this contract
Who was awarded the equipment contract by Palmer Plantation Mud 2?
COHEN was awarded this equipment contract by Palmer Plantation Mud 2, as recorded on June 19, 2024.
What type of contract is this?
This is a Equipment contract, documented as a report record.
Where was this contract approved?
This contract appears in palmer-plantation-mud-no-2-engineering-report-june-19-2024_d85.pdf (Report), dated June 19, 2024 from Palmer Plantation Mud 2. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does COHEN hold?
COHEN may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Palmer Plantation Mud 2 currently buying?
Explore Palmer Plantation Mud 2's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.